Project schedule risk, made legible

A date isn’t
a forecast.

A programme says March. RiSiQ shows how much confidence belongs behind that date — and what could move it.

Think of it as a weather forecast for your project.

No credit or debit card required

Schedule forecast

One date. A range of outcomes.

Illustrative cumulative curve of possible project durations. The programme date carries about 35% confidence; the 80% date is 455 days.
Programme date~35% confidence
80% finish date455 days
The programme date is one point on the curve, not the answer. Illustrative example — synthetic schedule, not a live project forecast.

A schedule gives you a date.
A forecast tells you how much to trust it.

Confidence, not certainty.
01 — The forecast

“It’s on track.”
At what probability?

A schedule gives you a date. RiSiQ gives you a way to judge how much to trust it — so a forecast can inform the decision, instead of dressing an estimate up as a promise.

The programme

“We finish in March.”

A date, without a measure of confidence.
02 — What you actually get

Three things to take
into the next meeting.

A clearer view of the date, the drivers and the cost — without pretending there is no uncertainty.

01

A percentage, not just a date

See the chance of finishing by your target — not only the target the programme prints.

FINISH-DATE CONFIDENCE
Programme
~35%
80% date
455 days
02

The few things that move the finish

Of the many things that could go wrong, three or four can move the end date most. RiSiQ ranks those drivers and shows their impact in days, so effort goes where it can help.

Illustrative horizontal ranking of six work packages by how many days of finish-date spread they drive. Fabrication and procurement lead at 13 days each.
Illustrative driver analysis · fabrication and procurement lead at 13 days each
03

The price of delay, in ringgit

Understand what being three months late could cost, in a number you can take to a board, a bank or a client.

Illustrative distribution of total time-related cost. The median is RM 3.6 million and the 80th percentile is RM 3.8 million.
Illustrative time-related cost distribution · median RM 3.6m · 80th percentile RM 3.8m
And a written report

Bring the assessment — not just the date.

Executive summary, S-curve, cost distribution, joint confidence, work-package health and ranked drivers. Ready to put in front of a board, a bank or a client.

See what RiSiQ can show
03 — Why it matters

Better questions.
Better choices.

The point isn’t to predict the future with certainty. It’s to make the uncertainty useful before you commit to a decision.

A

“On track at what probability?”

Replace a reassuring nod with a number you can discuss.

B

“What’s your independent view?”

When a contractor asks for more time, bring your own assessment to the conversation.

C

“What does each option cost?”

Compare accepting a delay with paying to avoid it — before you choose.

BACKTEST · COMPLETED PROJECT
Illustrative backtest with a predicted P10 to P90 band and the actual finish marked inside it.
The predicted band — and where the project actually finished. Illustrative example.
04 — Start with evidence

Test the forecast
before you trust it.

Use a project that has already finished. Give RiSiQ the programme as it stood two years ago. See whether it would have warned you — before you pay anything.

Create an account to test a project
05 — Built for trust

Honest about
what it can’t know.

A useful forecast earns trust by showing where it is weak — not by pretending to be certain.

Not a verdict on your contractor

RiSiQ won’t tell you whether someone is dishonest.

Not a replacement for project leadership

It informs the person running the project; it does not replace them.

Concurrent risks can be understated

When several things go wrong together — bad weather, a supplier failure and a short crew — RiSiQ may understate the risk rather than overstate it. The report says so.

Entry tier — Start with evidence

Start where
the risk is.

A fraction of what a consultant charges for the same analysis — an analysis many projects skip because it is too expensive to justify.

No payment before you test it.
No promised outcome — just a forecast to judge.
BasicFor your next decision
30-day free trial
RM 599/ month
RM 3,420 / 6 monthsRM 6,500 / year
  • ✓1 project
  • ✓5 users
  • ✓3 reports per month
Try it on a completed project

Trial: 1 user · 1 project · 3 reports per month. No card required and no overage charge.

MAKE “WE HOPE” ACTIONABLE

80% — and here’s
what would make it 90%.

Illustrative wording, not a forecast result. A sentence you can act on in a meeting.

80%90%

Confidence becomes a conversation about what could change.

Test RiSiQ on a finished project